Hi,
I see that wait time helps between the "Operations" within a routing.
I have Material A (header) and component B.
Routing for A :R1 - one operation OP1 (Planned order A)
Routing for B: R2.- One operation OP2 (Planned order B)
I have separate routing for A and B. I need to start OP2 always 30 mins later.
R1:Op1: 8.00 - 9.00 am (Planned order A)
R2 :Op2 : 9.30 - 10 am (Planned order B)
Any suggestions.